The float glass line has been completely renovated, the technology improved. The investment is a commitment to Gladbeck, securing 530 jobs.
Restart of the float line GL2 in Gladbeck

The brief pressure of plant manager Reinhard Regulski on the red button was rather unspectacular compared to the investment sum, which was thus put into operation. NSG Group spent around EUR 30 million on the modernization of the float glass line at the Gladbeck plant, which was started at the push of a button on Wednesday morning.

At the end of April, the production line GL2, which produces flat glass primarily for the automotive industry, had been taken out of service for the planned cold repair. For a total overhaul of the 24/7 installation, which must be done every 15 years or so. Because at an operating temperature of more than 1500 degrees, the glass melt is produced in a gigantic furnace with a capacity of 1800 tons, which continues to spread over a huge tin-filled bath to a glass ribbon whose thickness can be determined. The result is flat glass (float glass) in thicknesses of 1.5 to 12 millimetres, which is cut to size and further processed (coated) to be used throughout Europe in the automotive and construction industry (window glass). Building glass is primarily produced on the first float-glass line in Gladbeck, (GL1), which was still in operation during the repair period. 

Production starts in August

The complete renewal of the technique of the glass melting furnace can improve the energy efficiency of the plant, reduce gas consumption and reduce carbon dioxide emissions by 20 percent.

In addition, the emission control systems and dust filters have been modernized. In addition, new cutting tables and cutting technology for stacking de-cut glass plates were installed at the cold end of the float line.

The gentle heating up of the furnace to 1600 degrees will take about three weeks, so that production will begin in August.

The investment is a clear commitment to the city and a positive signal for the domestic economy.

We value your privacy

We use cookies on this website for analytics, remarketing, social media (optional) and content (essential) purposes.

By clicking ‘Accept All’ you consent to the use of cookies for non-essential functions and the related processing of personal data. Alternatively you can reject non-essential cookies by clicking ‘Essential Only’. You can adjust your preferences at any time by visiting our Cookie Policy and access the settings on that page.

For more information please read our